Task 1

PMIA (Port Moresby)

12345678
100%
1 / 2
Existing Layout

Existing Facilities

번호(①②③)를 누르면 도면에서 그 시설의 위치를 짚어줍니다
Adequate — meets requirements for the current fleetDeficiency — upgrade or remediation requiredTo Confirm — data outstanding for the 90% report

Airside Facilities

Ch. II §1 · 24 items · 9 deficiency · 8 to confirm

Aerodrome Reference CodeDeficiency

  • Principal international gateway and domestic hub, ~8 km east-north-east of the Port Moresby CBD, bounded by the Hubert Murray Highway to the north and by terrain rising toward Bootless Bay to the south
  • Developed from Jacksons Field (1942); the present form results from progressive upgrades through the 1970s–80s and from asphalt overlay, lighting renewal and apron extension works completed from 2010 onward
  • Currently operates under Aerodrome Reference Code 4-D supporting B767-300 and A330 operations; transition to Code 4-E for the B777-300ER is the primary objective driving the airfield development scenarios
  • A cemetery serving local families for several generations occupies a large area near the south-western site boundary
ARC 4-DAYPY / POM8 km ENE of CBDTarget 4-E

Runway 14L/32R — InstrumentAdequate

  • Single instrument runway, true bearing 148.63°/328.63° (magnetic 142°/322°), 2,750 m × 45 m grooved asphalt with nil slope
  • Threshold elevations 103 ft (14L) and 128 ft (32R); TDZ elevations 102 ft and 135 ft
  • Declared distances: TORA / ASDA / LDA 2,750 m, TODA 2,810 m (14L) and 2,870 m (32R); clearway 60 m (14L) and 120 m (32R)
  • Aircraft in excess of 40,000 kg may perform 180° turns only on the widened concrete runway ends
2,750 × 45 mGrooved asphaltTORA / ASDA / LDA 2,750 mStrip 2,870 × 280 m

Runway 14R/32L — General AviationAdequate

  • Parallel bitumen-sealed strip retained from the original Jacksons Field, 1,300 m × 30 m, sloping 0.6% down to the north-west, with a 60 m stopway
  • TORA and LDA 1,300 m; ASDA 1,360 m
  • Available only to aircraft of MTOW ≤ 23,000 kg and not available for night operations
  • Its retention, and any alternative use of the land it occupies, are examined in Chapter VI within the updated land use plan
1,300 × 30 mBitumen sealedMTOW ≤ 23,000 kgDay VFR only

Pavement Strength & ACR-PCR TransitionTo Confirm

  • Strengths remain published in PCN format (PNG AIP, AYPY AD 2-11, 07 September 2023); ICAO Annex 14 Amendment 13-B brought the ACR-PCR method into force in 2024
  • The main runway, principal parallel and connecting taxiways, cargo apron and VIP apron are rated PCN 70/F/C/X/U asphalt — reported adequate to B747-400 maximum landing weight
  • The secondary runway is PCN 20/F/C/Y/U chip seal (~33,000 kg)
  • Apron strengths range from PCN 50 asphalt (domestic north) and PCN 40 asphalt (PNGDF south) down to PCN 10–15 chip seal on the general-aviation aprons
  • Conversion to ACR-PCR and assessment of the PCN 70 rating against the B777-300ER are carried into the Chapter V runway-extension pavement works
PCN 70/F/C/X/U main RWYPCN 50 / 40 apronsPCN 10–15 GAConversion due

RESA & Runway StripTo Confirm

  • A RESA of 90 m × 90 m is available for RWY 32R take-off
  • Existing RESA and runway strip dimensions are to be confirmed by site survey
  • Where they fall short of the Annex 14 Code 4-E recommendation, the consequences for runway length available at B777-300ER MTOW — use of declared distances, displaced thresholds or an arrested deceleration system — are addressed in Chapter V (Development Alternatives)
RESA 90 × 90 mSurvey requiredAnnex 14 Code 4-E

Taxiway SystemDeficiency

  • A parallel taxiway extends the full length of the instrument runway on the apron (western) side, connected to the runway by a series of right-angle exit taxiways
  • No rapid exit taxiways (RETs) are presently provided; the configuration constrains hourly runway capacity below the single-runway potential and limits stand-inventory flexibility
Full-length parallelRight-angle exitsNo RETs

International ApronAdequate

  • The first of the four functional apron precincts
  • Fronts the International Terminal Building and accommodates wide-body Code-E and narrow-body Code-C operations, on contact stands served by passenger boarding bridges and on remote stands served by apron bus from the secure side of the terminal
Fronts the ITBCode-E + Code-CContact (PBB) + remote

Domestic ApronAdequate

  • The second apron precinct
  • Fronts the Domestic Terminal Building and is dedicated to Code-C narrow-body and smaller regional turboprop operations, with walk-out boarding and no passenger boarding bridges provided in the present configuration
Fronts the DTBCode-C + regional turbopropWalk-out boarding

General Aviation & Maintenance ApronsAdequate

  • The remaining two apron precincts are (iii) the general aviation apron, reviewed under General Aviation, and (iv) the maintenance apron together with the Air Niugini base hangar apron, reviewed under Aircraft Maintenance
GA apronMaintenance apronAir Niugini base hangar

Stand Inventory & Apron PavementTo Confirm

  • Stand counts, individual stand dimensions, MARS (Multiple Aircraft Ramp System) configurations and pavement strength (ACR-PCR) across the four apron precincts are to be documented and confirmed with NAC in the 90% report
Stand counts TBCMARS configuration TBCACR-PCR TBC

Ground Lighting, Marking & SignageDeficiency

  • Visual aids are configured to support Category I ILS precision approaches to RWY 14L and 32R
  • High-intensity runway edge lighting, green threshold and red runway-end lighting are installed, with medium-intensity lighting along the parallel and exit taxiways
  • Touchdown-zone lighting, runway centreline lighting and an approach lighting system are not provided — TDZ and centreline lighting are both required for Category II operations and would be delivered in conjunction with any future CAT II ILS upgrade
  • Runway and taxiway markings, mandatory instruction signs and information signs are understood to be in general conformance with ICAO Annex 14 Chapter 5
HIRLMI taxiway lightingNo TDZ / centrelineNo ALS

Precision Approach (ILS & PAPI)Deficiency

  • Category I Instrument Landing Systems serve both RWY 14L and 32R, with PAPIs installed both sides at 3° (MEHT 55 ft) near each threshold
  • The ILS equipment is approximately 15 years old and therefore at the end of its useful life; given occasional limited-visibility conditions at PMIA, consideration should be given to installing a Category II ILS, or an upgradeable Category I to Category II system, as part of the replacement
  • The ILS facilities stand 49 ft (15 m) AGL, 135 m from the RWY 14L centreline and 127 m from the RWY 32R centreline
CAT I both endsPAPI 3° / MEHT 55 ftEquipment ~15 yrsCAT II option

Navigation Aids (VOR/DME & PBN)Deficiency

  • A VOR/DME beacon provides the published instrument approach procedure suite alongside the ILS and performs a critical function as both an approach aid and an en-route navigation aid; this equipment is also fast approaching the need for replacement
  • Area Navigation (RNAV, GNSS) and Required Navigation Performance (RNP) approach procedures are published for both runway directions, providing satellite-based approach capability independent of the conventional navaid infrastructure
VOR/DMERNAV (GNSS) / RNPReplacement due

Air Traffic SurveillanceAdequate

  • Surveillance is provided by Niusky Pacific Ltd through ground-based secondary surveillance equipment supplemented by Automatic Dependent Surveillance-Broadcast (ADS-B) coverage
  • There are no plans to utilise a Ground-Based Augmentation System (GBAS)
SSR + ADS-BNiusky Pacific LtdNo GBAS planned

Control Tower & Air Navigation ServicesTo Confirm

  • The control tower is located on the north-eastern side of the airfield with unobstructed line of sight to both runway thresholds, the parallel taxiway and the international and domestic aprons; air navigation service is provided from it by Niusky Pacific Ltd
  • Equipment configuration and remaining service life of the tower cab and associated communications and surveillance fit-out are to be confirmed with Niusky Pacific and reported in the 90% report, together with the availability of a contingency ATC operating position should the cab become unusable
NE side of airfieldUnobstructed line of sightContingency position TBC

Meteorological ObservationAdequate

  • A weather station west of the international terminal, beside the power house and gas production facility, records temperature, pressure and wind direction
  • The AWOS comprises three sensor locations — one at each runway threshold and one at the runway mid-point; a runway extension would relocate the mid-point and RWY 32R threshold sensors together with the adjacent approach lighting and PAPIs
  • The aerodrome reference temperature is retained at 33 °C (November mean daily maximum 32.7 °C over 2021–2025, ~0.5–1.0 °C above the 2004–2008 record)
  • The 1986 wind rose shows the existing runway orientation available 100% of the time below 20 kt crosswind and 98% at 10 kt or less, meeting ICAO criteria
AWOS — 3 sensorsReference temp 33 °CCrosswind criteria met

Airfield Drainage & Design StormTo Confirm

  • Stormwater discharges to the natural drainage system south of the airfield (direction to be confirmed), and performance of the network during wet-season peak events is unverified
  • Gumbel frequency analysis of annual maximum daily rainfall gives a 24-hour design rainfall of 236 mm (1-in-10-year), 325 mm (1-in-50-year) and 362 mm (1-in-100-year), or approximately 270 / 375 / 415 mm including a 15% climate change allowance
  • Surface drainage should be designed for the 1-in-5-year event, main drains and culverts for 1-in-50-year, and flood protection for the 1-in-100-year event with climate allowance
  • Water channels and conduits passing through or below the perimeter must be inspected regularly and kept secured
1:100 = 362 mm/24 h+15% climate allowanceDischarge to the south

ARFF (Rescue & Fire Fighting)Deficiency

  • Services are presently understood to be provided at ICAO Category 7, with the station adjacent to the airfield and response paths achieving the Annex 14 three-minute maximum response criterion to all points of the runway
  • Transition to ICAO Category 9 would be required to support routine B777-300ER operations and is included in the Phase B capital programme in Chapter VII
  • Appliance inventory, agent delivery capacity, manning levels, out-of-service durations, and the availability of retention ponds or other supplementary water sources to replenish appliances during a sustained incident are to be confirmed with NAC ARFF in the 90% report
ICAO Category 73-min response metCAT 9 required for B777

Aviation Fuel SupplyTo Confirm

  • Jet A1 is supplied at PMIA by Puma Energy through into-plane refuelling
  • Storage capacity, tank age and condition, hydrant versus tanker refuelling coverage, and the number of days of on-site fuel reserve required under the National Civil Aviation Security Programme are to be confirmed with NAC and Puma Energy in the 90% report
  • Avgas arrangements for the GA fleet — storage location, capacity and delivery method — are likewise outstanding
Jet A1 · Puma EnergyInto-plane refuellingCapacity & reserve TBC

Power & Standby GenerationTo Confirm

  • The primary electrical supply is supplemented by airport-side standby generators supporting airfield ground lighting, navaids and ARFF as essential loads
  • Contingency and redundancy arrangements for both the electricity and water supplies are to be confirmed with NAC and reported in the 90% report
Airport-side gensetsAGL / navaids / ARFFRedundancy TBC

Perimeter Security & FencingDeficiency

  • Sections of the perimeter do not meet the ICAO-recommended security standard: Doc 8973 recommends a minimum 2.44 m (8 ft) fence along the entire boundary augmented by inclined barbed or razor wire, and there is no perimeter CCTV, security lighting or Perimeter Intrusion Detection System on the landside boundary
  • The June 2026 review further found that fencing near the two terminals lacks barbed or razor wire along sections of its top; that several buildings stand close enough to the airside fence to facilitate access over it, contrary to Annex 17; that there is no consistent 3 m clear strip on either side; and that the fence is not continued below ground to deter burrowing
  • Obstructing vegetation must be cleared and controlled, and buildings overlooking the fence equipped with CCTV and physical deterrents
  • A full perimeter upgrade is recommended — the most significant deficiencies are within the cargo precinct
Below Doc 8973 (2.44 m)No CCTV / lighting / PIDSNo 3 m clear stripFull upgrade needed

Perimeter Patrols & Airside Access ControlDeficiency

  • Details of the number and regularity of security patrols were not available at the time of the review; patrols should be frequent, at irregular intervals and maintained 24/7
  • The perimeter security road is in need of repair — rapid access by security or fire services to all points of the perimeter is currently difficult
  • During the June 2026 review it proved possible to drive unchallenged through a gate on the eastern side of the airport and to access the airside adjacent to the PNGDF clinic, where the airside gate was open and unmanned — a significant breach leaving the PNGDF and Aus/NZ (ANZAC) areas vulnerable
  • Gate manning, challenge procedures and periodic access-point audits should be strengthened in accordance with Annex 17 / Doc 8973
Unmanned gate observedSecurity road repairDoc 8973 Ch. 11

Security & Emergency Contingency ProvisionsTo Confirm

  • The following are to be confirmed with NAC and reported in the 90% report: designation of an isolated aircraft parking position at least 100 m from other aircraft, buildings, public areas and the airport fence (ICAO Annex 17 and Doc 8973); an isolated storage area for baggage intended for bomb-disposal intervention, offering a safety perimeter of approximately 150 m radius (ICAO Doc 9184); and the existence of a Security Operations Centre and a geographically separate Emergency Operations Centre
Isolated parking ≥ 100 mBaggage area ~150 m radiusSOC / EOC TBC

Aerodrome Hazards & WildlifeDeficiency

  • Published aerodrome hazards comprise the Digicel Tower at approximately 900 ft AMSL at Savannah Heights, 2.5 NM west of the aerodrome; a road aligned with RWY 14L in the final-approach area; bird and flying-fox activity; and reported unauthorised drone, sky-lantern and laser activity within the Jacksons TMA
  • Regular runway inspections are undertaken by the airport operator; the bird-strike record over the previous five years is to be obtained from NAC operations and reported in the 90% report
Digicel Tower ~900 ftRoad on 14L approachBird / flying-foxDrone & laser reports

Passenger Terminals

Ch. II §2 · 6 items · 4 deficiency

Terminal Configuration — Two Separate BuildingsDeficiency

  • PMIA operates two physically separate passenger terminal buildings, the International Terminal Building (ITB) and the Domestic Terminal Building (DTB)
  • They are accessed from separate landside roads and share no airside or landside passenger transit: passengers connecting between domestic and international flights must exit the originating terminal, transit landside and re-enter the destination terminal as new origin passengers, with the attendant security re-screening, immigration formality and baggage re-checking
  • Both trace their present configuration to progressive development from the 1980s with subsequent extensions, finishes upgrades and processor renewals under NAC capital expenditure, and both are operated by NAC under direct management with retail concessions and ground handling under separate contracts
ITB + DTB separateNo airside / landside transitNAC operated

International Terminal Building (ITB)Adequate

  • Located on the western side of the landside precinct, serving all international scheduled services
  • Six airline tenants operate from the ITB: Air Niugini (national carrier and base operator, with rotations to Brisbane, Sydney, Cairns, Manila, Singapore, Hong Kong and Honiara and a Paradise Lounge on the secure side), Qantas, Virgin Australia, Philippine Airlines, Singapore Airlines and Cathay Pacific
  • Departures processing comprises a row of check-in counters serving combined manual and Common Use Self Service (CUSS) functionality, security screening lanes and immigration desks, with duty-free retail, food and beverage and an airline lounge on the secure-side concourse
  • Arrivals comprise immigration, baggage reclaim and customs onto the meeter-and-greeter forecourt
  • Aircraft are accommodated on a combination of contact stands with passenger boarding bridges and bus-served remote stands, with the stand inventory to be confirmed in the 90% report
6 international carriersManual + CUSS check-inPBB contact + bus remote

Domestic Terminal Building (DTB)Adequate

  • Located adjacent to the ITB on the same landside frontage and serving all domestic scheduled services; the layout and processor inventory are documented in the NAC PMIA Redevelopment Project drawing series (NAC-PMIA-DTB-G05, DTB Reconfiguration & Expansion Project, March 2025)
  • The building has two levels: the ground floor accommodates the public concourse with multiple rows of check-in counters, two baggage make-up areas, two baggage break-down areas, two baggage claim carousels, airline offices, customer-services facilities and the meeter-and-greeter forecourt; the first floor accommodates additional airline office space, operations management and back-of-house facilities
  • Tenants are Air Niugini, PNG Air and Mission Aviation Fellowship, serving Lae, Mount Hagen, Madang, Wewak, Goroka, Tabubil, Kavieng, Rabaul and the provincial centres
2 levels2 make-up / 2 break-down2 claim carouselsAir Niugini · PNG Air · MAF

DTB Aircraft Accommodation & Commercial OfferDeficiency

  • Walk-out boarding is provided for Code-C narrow-body operations (B737, F70/F100), Code-B regional turboprop operations (Q400, Twin Otter) and Code-A general aviation visiting operations; no contact stands with passenger boarding bridges exist in the present DTB configuration
  • Retail and food-and-beverage provision is more limited in scale than the ITB, reflecting the shorter dwell times, principally domestic passenger profile and lower per-passenger commercial revenue benchmark of the regional turboprop and narrow-body domestic market
Walk-out boardingCode-A / B / CNo PBBsLimited retail & F&B

Cross-Terminal Connectivity & AccessibilityDeficiency

  • Connectivity between the ITB and DTB is via the public landside road network only; no covered passenger walkway, internal transit corridor or shared check-in functionality is provided
  • Any of the terminal development options examined in Chapter V would resolve this deficiency
  • On accessibility, the Consultant is advised that there is accessible landside parking, ramped access at terminal entries, lifts to upper levels in both terminals and assisted-mobility services on request from the operating carrier; a full assessment of universal-design and inclusive-facility requirements — accessible toilets, nursing / lactation rooms, tactile and Braille signage and provisions for persons with disabilities — is provided in Chapter VII
Road link onlyNo covered walkwayPRM review in Ch. VII

Terminal Security & Forecourt ProtectionDeficiency

  • Reviewed in June 2026 against ICAO Annex 17, Doc 8973 Chapter 11 and IATA reference material
  • Security inside both terminals causes no concern: doors are swipe-controlled or securely locked, hinges are not externally removable, CCTV is in clear view and security personnel are prevalent and attentive
  • The deficiencies lie at the frontage
  • The building frontage does not achieve the 30 m clear stand-off recommended by Doc 8973, and full compliance would be difficult and costly given the high ground in front of both buildings — as mitigation, additional speed bumps should be provided and parking directly in front expressly prohibited
  • More bollards are needed to deter vehicle intrusion, the supporting columns obscure CCTV sightlines, and the main car park should be lit at night and covered by CCTV
  • Blast resistance of the DTB’s large glazed areas could not be verified and should be confirmed, with blast-mitigating film or laminated replacement where required
  • Any future inter-terminal walkway should be protected by a solid wall between airside and landside and/or strengthened laminated glazing that cannot splinter
In-terminal security positive30 m stand-off not metBollards & sightlinesGlazing rating TBC

Cargo

Ch. II §3 · 8 items · 7 deficiency

Cargo Precinct — Ownership & RoleAdequate

  • PMIA is the principal aviation cargo gateway for Papua New Guinea
  • The facility is owned by the National Airports Corporation and operated by Air Niugini under a ground-handling arrangement, within a single precinct physically separated from the passenger terminals, with dedicated airside access from the cargo apron and dedicated landside access for road freight
  • The absence of a continuous national road network — particularly between the National Capital District and the highland provinces — makes domestic air freight an essential lifeline service, with a higher proportion of perishables, medical supplies and emergency response cargo than at a comparable coastal capital airport
  • International outbound cargo is dominated by primary-sector exports, with tuna fishery products, Highland coffee and vanilla among the principal commodities
  • Observations are based on a site inspection of the cargo precinct undertaken on 24 June 2026
NAC ownedAir Niugini operatedSite inspection 24 Jun 2026

Cargo Warehouse — Condition & CapacityDeficiency

  • A single-warehouse configuration accommodates the receipt, screening, storage and make-up of both domestic and international freight, with landside road-freight access on one elevation and airside access to the cargo apron on the opposite elevation
  • The warehouse is dated and in poor structural repair; its narrow footprint constrains internal circulation and is inadequate to accommodate forecast throughput growth or the installation of additional screening and surveillance equipment
  • Extension or replacement of the building will be required
Single warehousePoor structural repairNarrow footprintExtend or replace

Materials HandlingDeficiency

  • Cargo is moved from the landside unloading point to the warehouse on a temporary conveyor and is subsequently off-loaded manually; both the inbound transfer and the in-warehouse handling are predominantly manual, as is handling at the apron interface
  • Throughput and handling efficiency would be materially improved by mechanised handling using pallets or Unit Load Devices with fixed conveyor and roller systems, which would also reduce aircraft ground time
Temporary conveyorPredominantly manualMechanise with ULDs

Screening Equipment & RedundancyDeficiency

  • Freight passing into the warehouse is screened through a security scanner prior to storage, which is consistent with good practice, although the associated handling around the scanner remains manual
  • Screening is provided by a single domestic and a single international scanner with no standby unit — failure of either would halt the corresponding cargo stream, and dual (N+1) screening capability should be provided for each
  • Domestic cargo uplifted to international services is re-screened through the international scanner before transfer; reliance on that single unit for both direct and transferred international freight creates a processing bottleneck
1 domestic + 1 internationalNo standby unitN+1 requiredTransfer bottleneck

Cold-Chain StorageDeficiency

  • Three cold-storage rooms are provided, of which only one is currently serviceable
  • Reinstatement of the two non-operational rooms is required to restore full cold-chain capacity for PMIA’s perishable export traffic
  • As perishable export volumes grow, cold-chain capacity will need to be expanded beyond reinstatement of the existing rooms, at a scale determined by the cargo capability requirements in Chapter IV
3 rooms / 1 serviceableReinstatement requiredExpansion in Ch. IV

Cargo Security & Vehicle AccessDeficiency

  • The cargo precinct perimeter does not meet ICAO security requirements: fencing falls below the Doc 8973 minimum of 2.44 m augmented by inclined barbed or razor wire, and there is no perimeter CCTV, security lighting or PIDS on the landside boundary; obstructing vegetation must be cleared and controlled
  • Cargo is stored under CCTV coverage, but the current camera layout leaves blind spots that should be eliminated as part of a security upgrade
  • Road-freight vehicles enter through a manually operated swing barrier leading directly to the unloading bay, with no air-lock (sally-port) arrangement and gate and forecourt areas insufficient for vehicles to turn around in accordance with ICAO guidance
  • No separate exit is provided for cargo vehicles as recommended by IATA, so inbound and outbound traffic shares a single controlled point, limiting throughput and security segregation
Perimeter below standardCCTV blind spotsNo air-lockNo separate exit

Cargo Apron & Airside InterfaceDeficiency

  • The cargo warehouse is located a considerable distance from the aircraft stands it serves, introducing several minutes of delay in each direction when moving freight between the warehouse and the apron
  • Combined with the single international scanner, this extends the time required to transfer domestic cargo onto international services and compounds the screening bottleneck
  • Relocation, or a closer cargo facility, is to be assessed within the development options
Distant from standsMulti-minute transfer delayRelocation to assess

Cargo Drainage & Flood ProtectionDeficiency

  • Flooding occurs at one end of the warehouse during heavy rainfall
  • A covered drainage gully should be provided along the landside edge of the cargo and adjacent buildings to channel storm water away from these high-value structures
Wet-season floodingCovered gully required

General Aviation

Ch. II §4 · 5 items · 1 deficiency · 2 to confirm

GA Precinct — Role & ConfigurationAdequate

  • General aviation comprises charter, corporate, mission-aviation and rotary-wing operations, concentrated in a dedicated precinct with its own apron, hangar accommodation and landside vehicle access, physically separated from the passenger terminal frontage; light fixed-wing VFR operations are additionally served by strip 14R/32L
  • GA performs a materially more significant transport function in PNG than at comparable international gateways: with much of the country inaccessible by road, charter, mission-aviation and rotary-wing operators provide essential passenger, medical-evacuation and light-freight connectivity to provincial airstrips not served by scheduled carriers, and PMIA acts as the principal base and technical stop for this activity in the southern region
  • The precinct is therefore treated as core airport infrastructure rather than a discretionary land use
Dedicated precinctLifeline & medevac roleCore infrastructure

GA Apron, Hangars & TenanciesTo Confirm

  • The GA apron provides parking positions for light fixed-wing aircraft and helicopters; apron dimensions, pavement condition and strength (ACR-PCR), and the parking and tie-down inventory are to be documented and confirmed with NAC in the 90% report
  • Hangar and workshop accommodation is provided under NAC ground leases to the resident charter, mission-aviation and helicopter operators, with the tenancy schedule, building condition and remaining lease terms likewise to be confirmed
Fixed-wing + rotary parkingNAC ground leasesInventory & lease terms TBC

Helicopter Operations & FBO ConceptAdequate

  • Rotary-wing operators including Helifix operate from the GA precinct alongside fixed-wing charter activity
  • A concept proposal prepared during the June 2026 review provides for an FBO / helicopter maintenance hangar incorporating a dedicated security facility, together with helicopter stands arranged along the airside/landside boundary that remain interchangeable with the fixed-wing GA parking stands; the proposal is examined in Chapter V (Development Alternatives)
Helifix + charterFBO / maintenance hangarInterchangeable stands

GA Segregation, Security & Access ControlDeficiency

  • In accordance with ICAO Annex 17, Doc 8973 and IATA reference material, general aviation should be segregated from commercial air transport operations with its own security-controlled landside-to-airside access
  • The June 2026 concept provides for a standalone GA security gate comprising an office for permanent security staff, a customs / immigration room staffed as required for international GA movements, a crash gate kept closed except for ARFF use or supervised vehicle access, and a follow-me vehicle to escort passengers and vehicles to and from aircraft
  • The security review also found that the water channel adjacent to the Helifix facility, although fitted with the grating required by ICAO, could be passed beneath, permitting unobtrusive airside access — all culverts, ducts and underground accesses wider than 80 cm should be closed, secured and/or controlled
  • Gate control and the screening arrangements applicable to charter passengers are to be reviewed against the National Civil Aviation Security Programme
Segregation requiredStandalone GA gateCulvert breach found

Land Use Pressure on the GA PrecinctTo Confirm

  • The principal planning issue affecting the GA precinct is not GA demand growth but competition for its land from the terminal, apron and commercial development options examined in Chapter V
  • Any relocation or consolidation of GA facilities is addressed there and in Chapter VI, together with the retention of strip 14R/32L and any alternative use of the land it occupies
Land competitionRelocation in Ch. V / VI14R/32L retention

Aircraft Maintenance

Ch. II §5 · 4 items · 2 deficiency · 1 to confirm

Maintenance Base — Air Niugini EngineeringAdequate

  • Aircraft maintenance at PMIA is anchored by the Air Niugini engineering base, which provides line and base maintenance for the national carrier’s fleet and line-maintenance support for third-party operators
  • The precinct comprises hangar and workshop accommodation with an associated maintenance apron and dedicated airside access, complemented by the light-aircraft maintenance undertaken within the general aviation precinct
  • On-airport capability is oriented to the narrow-body and turboprop fleet; heavy maintenance of wide-body aircraft is undertaken offshore, as is common for carriers of this scale
Line + base maintenanceNarrow-body / turbopropWide-body heavy offshore

Hangars, Maintenance Apron & CertificationTo Confirm

  • The dimensions, door clearances and structural condition of the Air Niugini hangars, and the largest aircraft type that can be fully enclosed, are to be confirmed with Air Niugini Engineering
  • Maintenance apron stand capacity, pavement strength (ACR-PCR) and any engine ground-running restrictions are to be confirmed with NAC
  • The scope of the approved maintenance capability (line and base checks by aircraft type), engineering staffing and the extent of reliance on offshore heavy maintenance are likewise to be reported in the 90% report
Hangar dimensions TBCGround-running limits TBCCapability scope TBC

Hangar Precinct SecurityDeficiency

  • The June 2026 security review found several side doors of the Aus/NZ (ANZAC) hangar open and accessible without challenge, leaving the hangar and the adjacent PNGDF area vulnerable to unauthorised airside access
  • Hangar-precinct access control — door discipline, intrusion alarms and CCTV coverage — should be brought into conformance with ICAO Annex 17 / Doc 8973 and the airport security programme
Open unchallenged doorsPNGDF area exposedAnnex 17 / Doc 8973

B777-300ER Readiness & MRO PotentialDeficiency

  • Routine operation of the B777-300ER design aircraft will require line-maintenance capability, ground support equipment and spares provisioning appropriate to the type; hangar access for a Code-E aircraft is not assumed in the present configuration
  • Rotary-wing maintenance currently undertaken within the GA precinct would be consolidated by the proposed FBO / helicopter maintenance hangar
  • The updated land use plan in Chapter VI safeguards expansion land for maintenance and MRO development, recognising the potential for PMIA to consolidate national maintenance activity as the fleet grows
Code-E hangar not assumedLine-maintenance upliftMRO land safeguarded

Landside Access & Parking

Ch. II §6 · 6 items · 4 deficiency · 2 to confirm

Access Configuration & ResilienceDeficiency

  • Landside access is from the Hubert Murray Highway, which bounds the airport to the north, via the terminal access road serving the ITB and DTB frontages, approximately 8 km from the Port Moresby central business district
  • Effectively all passengers, employees and visitors arrive by road — private car, taxi, hotel and company shuttle, or public motor vehicle (PMV); no rail or dedicated public-transport corridor serves the airport
  • A single principal access serves both terminals, which are reached from separate frontage roads with no direct transit link between them
  • Reliance on a single access point is a resilience concern — a blockage or security incident at the junction could sever landside access to the airport — and the provision of an alternative or emergency access route should be reviewed
Hubert Murray Highway~8 km from CBDRoad access onlySingle access point

Kerbside OperationDeficiency

  • Separate drop-off and pick-up kerbs are provided at the ITB and DTB
  • Kerbside demand is characterised by a high private-vehicle mode share and the extended dwell times associated with the meeter-and-greeter culture; congestion at schedule peaks was observed during the June 2026 site visit, and kerbside management and enforcement will be required as traffic grows
Separate drop-off / pick-upHigh private-car sharePeak congestion observed

Wayfinding & Pedestrian MovementDeficiency

  • Vehicular wayfinding between the highway junction, the two terminal frontages and the parking areas is limited and should be upgraded as part of any landside works
  • Pedestrian routes between the parking areas, the two terminals and the kerbsides are incompletely segregated from vehicular traffic and covered walkway provision is limited; pedestrian provision should be upgraded in conjunction with the inter-terminal connectivity improvements
Limited vehicular wayfindingIncomplete segregationLittle covered walkway

Parking InventoryTo Confirm

  • Surface car parks front the two terminal buildings; bay counts, occupancy profiles, tariff structure and revenue performance are to be confirmed with NAC and reported in the 90% report
  • Staff, tenant and government-agency parking is distributed across the landside precinct, with the inventory and its allocation likewise to be confirmed
Surface car parksBay counts & tariffs TBCStaff / tenant allocation TBC

Landside Security & Car Park SurveillanceDeficiency

  • The practice of issuing landside vehicle passes, and the surveillance and patrolling of parking areas adjacent to the terminal buildings, should be reviewed against ICAO Doc 8973: where car parking areas are located adjacent to terminal buildings, critical infrastructure or aprons, surveillance and patrolling regimes should be implemented, and unattended or long-stay vehicles at the terminal frontage should be monitored and removed where necessary
  • The main car park should be lit at night and covered by CCTV
Vehicle pass reviewLong-stay monitoringLighting + CCTV

Ground Transport & Future Landside DemandTo Confirm

  • Taxi, hotel-shuttle and PMV services operate from the terminal frontages; the adequacy of dedicated ranks, holding areas and PMV stops is to be reviewed against forecast demand in Chapter IV
  • Growth in passenger traffic will increase kerbside, parking and circulation demand ahead of terminal capacity in some periods; landside facility requirements are quantified in Chapter IV and the corresponding land provision is made in Chapter VI
Taxi / shuttle / PMVRanks & holding areas TBCRequirements in Ch. IV

Section 1

Aviation Demand Forecast

Annual Passengers
DomesticInternationalTotal
1,320,711490,76820251,658,689753,42320301,863,023948,55220352,107,7071,190,59320402,393,5921,493,46020451,811,4792,412,1122,811,5753,298,3003,887,052
Flight Movements
DomesticInternationalTotal
32,3835,029202542,6367,819203047,3179,779203553,12412,253204059,85715,320204537,41250,45557,09665,37775,177
Peak Hour Movements
Total
16.7202521.8203024.1203526.9204030.22045
Section 2

Facility Plan

Master-plan facility checklist (SOW Element 4). For each facility, mark whether it is Complete, Missing, or Needs Improvement.

✓ Complete 1✕ Missing 0△ Improve 8• Not assessed 0
Runway△Improve
Length, width & pavement strength for the critical aircraft (RDC).
Runway Strip / RESA△Improve
Graded strip and runway end safety areas to ICAA standards.
Crosswind Coverage✓Complete
Wind analysis — need for a crosswind runway from historical wind data.
Taxiway System△Improve
Parallel / connector taxiways and separation criteria.
Commercial Apron△Improve
Air carrier aircraft parking apron & gate stands.
GA Apron△Improve
General aviation aircraft parking apron.
Airfield Lighting△Improve
Runway / taxiway lighting, signs and markings.
Navigation Aids (NAVAIDs)△Improve
Airspace / OLS△Improve

Section 3

Economic Evaluation

Total Project CostTBD
B/C RatioTBD
NPVTBD
EIRRTBD
Notes / Methodology
Economic evaluation methodology and assumptions to be documented here.