PMIA (Port Moresby)
Passengers: Flexa adopted forecast (Base × S2). Movements and peak hour: each master plan's own series (Chapter Ⅲ/Ⅳ, Task 3 desktop study; checkpoints interpolated). Finance is indicative: NAC published charges net of the CASA remittance (Flexa v9), standing costs K60M PMIA (Flexa v9), K7M regional hubs and K2.5M provincial airports calibrated to the NAC Corporate Plan 2026–2030; PGK at constant 2026 prices. Hover a figure for its basis; apron stands are on Horonjeff.
Passenger forecast to 2045
Domestic and international passengers, 2011–2045. Actual to 2026 (muted), forecast after — Flexa 02_PAX_ADOPTED, National forecast, S2.
Runway capacity at the 2045 peak
Design peak-hour movements against the hourly capacity of the runway–taxiway system (IATA ADRM).
Chapter Ⅳ: right-angle exits ≈24 mov/h today; full-length parallel taxiway ≈44 mov/h (24 mov/h today). Heavy traffic density (ICAO) begins at 26 mov/h per runway.
Capital cost to the 2045 master plan
PMIA_Cost_Estimate_v7 (Flexa v9 quantities, PMIA CADIP BOQ unit rates), Scenario B — opening 2040. USD at 2026 prices, US$1 = K4.10; preliminaries (12.5 %) spread over the six elements. On-costs and the phase split are the ADB disbursement plan, money of the day.
| Element | US$ M | Share | Scope and basis | |
|---|---|---|---|---|
| Airside facilities | 195 | 41% | Earthworks and site enabling, airside pavement (runway extension, taxiways, aprons), drainage, AGL and apron services, CAT II ILS | |
| Passenger terminal | 174 | 36% | New unified passenger terminal 43,049 m², baggage systems, Administration Block 8,500 m², decommissioning of the existing terminals | |
| Landside facilities | 15.0 | 3% | Access road, parking and patrol road pavement | |
| Utilities | 29.1 | 6% | Utility works, security and ICT systems | |
| Other ancillary facilities | 58.1 | 12% | Relocated cargo terminal 6,810 m², ARFF Cat 9, ATC refit with A-SMGCS, Code E MRO hangar, GA precinct buildings, Jet A-1 expansion, fencing, demolition | |
| Land acquisition & resettlement | 7.3 | 2% | New site 250,000 m² at K120/m² (GoPNG counterpart); no households affected | |
| Construction cost (direct works) | 479 | 100% | US$ million at 2026 prices | |
| Design, supervision, training and PM | 80.9 | 17% | ||
| Taxes and duties (GoPNG) | 62.1 | 13% | ||
| Physical contingency | 27.3 | 6% | ||
| Price contingency | 72.0 | 15% | ||
| Financing charges during construction (ADB IDC) | 176 | 37% | ||
| Total at 2026 prices, excl. price contingency and financing | 649 | |||
| Total capital cost | 897 | 187% | total project cost incl. price contingency and financing charges | |
Development programme by phase
What each phase delivers, the demand level that triggers it (Chapter Ⅳ / Ⅶ), and its share of the capital cost.
| Phase | Period | Trigger | Principal works | US$ M |
|---|---|---|---|---|
| Short term | 2026–2030 | B777-300ER design aircraft; 2033 APEC meetings; peak hour enters the ICAO heavy-density band (26+ mov/h) about 2038 | Runway 14L/32R extended to its ultimate 3,500 m by 2030; GA precinct and the Air Niugini engineering base relocated (Phase 1, 2029), releasing ≈25,000 m² of apron for Code E stands | — NAC committed baseline — not in the v7 estimate |
| Medium term | 2031–2037 | Report Phases 2–4: Administration Block occupied 2031, new remote apron 2031, unified terminal (Option T-3) targeted 2032, cargo precinct 2035; Flexa v9 Scenario B design 2034–35 | New remote apron; Administration Block ≈8,500 m²; design and enabling works for the unified terminal; cargo precinct relocated and rebuilt; perimeter and security upgrade | 434 v7 disbursement 2034–2037 |
| Long term | 2038–2045 | Scenario B opening 2040; 2045 requirement of 47 passenger and cargo stands (20 contact), ITB ≈22,400 m² and DTB ≈22,700 m², 1,368 public parking spaces | Runway–taxiway–apron works 2036–39, terminal systems 2038–39, unified terminal opens 2040; GA precinct ≈130,000 m² by 2040; existing terminals decommissioned 2040–42 | 464 v7 disbursement 2038–2042 |