Dashboard · master plan 2045

PMIA (Port Moresby)

POM · Task 1 · 2045 targets against 2025 actual (movements and peak hour against the 2026 plan base) · Flexa adopted forecast (Base × S2)
Passengers
3.80M
3,803,107 pax / year · intl 37%
+110%vs 2025
Aircraft movements
55.2k
55,170 movements / year
+78%vs 2026
Air cargo
56.8k
tonnes / year · freight and mail
+74%vs 2026
Peak-hour movements
30.0
movements / hour · 0.054% of annual
+50%vs 2026
Design aircraft
Boeing 777-300ER
Code E · today Boeing 767-300ER (D)
Code D → E
Revenue
K226.2M
PGK / year · aeronautical + commercial
+116%vs 2025
Expenditure
K126.7M
PGK / year · operating cost (OPEX)
+53%vs 2025
Operating surplus
K99.5M
PGK / year · EBITDA basis · margin 44%
+353%vs 2025

Passengers: Flexa adopted forecast (Base × S2). Movements and peak hour: each master plan's own series (Chapter Ⅲ/Ⅳ, Task 3 desktop study; checkpoints interpolated). Finance is indicative: NAC published charges net of the CASA remittance (Flexa v9), standing costs K60M PMIA (Flexa v9), K7M regional hubs and K2.5M provincial airports calibrated to the NAC Corporate Plan 2026–2030; PGK at constant 2026 prices. Hover a figure for its basis; apron stands are on Horonjeff.

Passenger forecast to 2045

Domestic and international passengers, 2011–2045. Actual to 2026 (muted), forecast after — Flexa 02_PAX_ADOPTED, National forecast, S2.

DomesticInternational
20302,412,112
20352,799,685
20403,257,976
20453,803,107

Runway capacity at the 2045 peak

Design peak-hour movements against the hourly capacity of the runway–taxiway system (IATA ADRM).

68%of runway capacity used in 20450%100%
Peak hour 202620.0 mov/h
Peak hour 204530.0 mov/h
Runway capacity 204544 mov/h
Headroom14.0 mov/h

Chapter Ⅳ: right-angle exits ≈24 mov/h today; full-length parallel taxiway ≈44 mov/h (24 mov/h today). Heavy traffic density (ICAO) begins at 26 mov/h per runway.

Capital cost to the 2045 master plan

PMIA_Cost_Estimate_v7 (Flexa v9 quantities, PMIA CADIP BOQ unit rates), Scenario B — opening 2040. USD at 2026 prices, US$1 = K4.10; preliminaries (12.5 %) spread over the six elements. On-costs and the phase split are the ADB disbursement plan, money of the day.

estimate
ElementUS$ MShareScope and basis
Airside facilities19541%Earthworks and site enabling, airside pavement (runway extension, taxiways, aprons), drainage, AGL and apron services, CAT II ILS
Passenger terminal17436%New unified passenger terminal 43,049 m², baggage systems, Administration Block 8,500 m², decommissioning of the existing terminals
Landside facilities15.03%Access road, parking and patrol road pavement
Utilities29.16%Utility works, security and ICT systems
Other ancillary facilities58.112%Relocated cargo terminal 6,810 m², ARFF Cat 9, ATC refit with A-SMGCS, Code E MRO hangar, GA precinct buildings, Jet A-1 expansion, fencing, demolition
Land acquisition & resettlement7.32%New site 250,000 m² at K120/m² (GoPNG counterpart); no households affected
Construction cost (direct works)479100%US$ million at 2026 prices
Design, supervision, training and PM80.917%
Taxes and duties (GoPNG)62.113%
Physical contingency27.36%
Price contingency72.015%
Financing charges during construction (ADB IDC)17637%
Total at 2026 prices, excl. price contingency and financing649
Total capital cost897187%total project cost incl. price contingency and financing charges
By element
By phase · ADB disbursement plan, money of the day (Scenario B works 2034–2042)
Short term 2026–2030—
Medium term 2031–2037434 · 48%
Long term 2038–2045464 · 52%
TotalUS$ 897 M
Per 2045 passenger: US$ 236 · per added passenger 2025→2045: US$ 450

Development programme by phase

What each phase delivers, the demand level that triggers it (Chapter Ⅳ / Ⅶ), and its share of the capital cost.

PhasePeriodTriggerPrincipal worksUS$ M
Short term2026–2030B777-300ER design aircraft; 2033 APEC meetings; peak hour enters the ICAO heavy-density band (26+ mov/h) about 2038Runway 14L/32R extended to its ultimate 3,500 m by 2030; GA precinct and the Air Niugini engineering base relocated (Phase 1, 2029), releasing ≈25,000 m² of apron for Code E stands—
NAC committed baseline — not in the v7 estimate
Medium term2031–2037Report Phases 2–4: Administration Block occupied 2031, new remote apron 2031, unified terminal (Option T-3) targeted 2032, cargo precinct 2035; Flexa v9 Scenario B design 2034–35New remote apron; Administration Block ≈8,500 m²; design and enabling works for the unified terminal; cargo precinct relocated and rebuilt; perimeter and security upgrade434
v7 disbursement 2034–2037
Long term2038–2045Scenario B opening 2040; 2045 requirement of 47 passenger and cargo stands (20 contact), ITB ≈22,400 m² and DTB ≈22,700 m², 1,368 public parking spacesRunway–taxiway–apron works 2036–39, terminal systems 2038–39, unified terminal opens 2040; GA precinct ≈130,000 m² by 2040; existing terminals decommissioned 2040–42464
v7 disbursement 2038–2042