Ten provincial
airports.
One programme.
Prepared without a site survey. Every quantity here is drawn from records — the project demand forecast, the National Airports Corporation movement record, published schedules and the planning standards — not from inspection.
All ten, side by side
Sorted by 2045 passengers, largest first. Click any column heading to re-sort, or any row to open that airport's study summary.
| Airport | 2011 – 2045 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
| 1 | Goroka Airport GKA · Eastern Highlands Province | 259,813 | ×1.87 3.3%/yr | 1,808 m² +828 | 5 from 3 | $16.54m | $6.54 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 2 | Wewak Boram Airport WWK · East Sepik Province | 244,457 | ×1.71 2.8%/yr | 1,707 m² +683 | 4 from 3 | $15.17m | $6.37 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
Passengers grow ×1.71 to 244,457 a year by 2045. That needs 683 m² more terminal and 1 additional aircraft stand — $15.17m in 2026 prices, $21.38m as actually spent. Passengers rise faster than flights because the average aircraft grows from 55 to 68 seats. The 2045 peak hour is 95 passengers — that single moment, not the annual total, is what the terminal is sized for. The airport in 2026 and in 2045
2045 stands are 3 Code C commercial positions and 1 for general aviation and light aircraft. Capital cost
Spend by phase
The $6.22m difference is price escalation, not extra work. Recovering the investment needs $6.37 per passenger in 2045 — $1.10m a year of capital charge plus $0.45m of operating and maintenance, spread over 244,457 passengers. Runway 10/28, 1,595 m × 30 m, asphalt Elevation 5.8 m · Code 3ⅡC · Design aircraft Fokker 100 · Lit Routes 2025 POM 936 · VAI 354 · MAG 212 · HGU 104 · LAE 105 — Port Moresby is 936 of the 1,711 departures. Committed works Wewak was deferred from CADIP tranche 1 to tranche 3, where the scope is pavement strengthening and a new terminal building. Full study: PNG AMPC Desktop Study-WWK.docx | ||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 3 | Kimbe Hoskins Airport HKN · West New Britain Province | 206,990 | ×1.96 3.6%/yr | 1,465 m² +708 | 3 from 3 | $13.22m | $6.56 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 4 | Madang Airport MAG · Madang Province | 169,523 | ×1.77 3.1%/yr | 1,211 m² +543 | 3 from 2 | $14.04m | $8.50 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 5 | Kavieng Airport KVG · New Ireland Province | 164,609 | ×2.14 4.1%/yr | 1,158 m² +624 | 3 from 2 | $14.20m | $8.86 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 6 | Alotau Gurney Airport GUR · Milne Bay Province | 103,188 | ×1.63 2.6%/yr | 729 m² +283 | 2 from 2 | $10.92m | $10.86 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 7 | Vanimo Airport VAI · West Sepik Province | 88,447 | ×1.78 3.1%/yr | 624 m² +259 | 2 from 2 | $10.70m | $12.42 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 8 | Manus Momote Airport MAS · Manus Province | 84,762 | ×1.77 3.1%/yr | 603 m² +279 | 2 from 2 | $10.73m | $12.99 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 9 | Buka Airport BUA · Autonomous Region of Bougainville | 73,091 | ×1.73 2.9%/yr | 490 m² +198 | 2 from 2 | $10.33m | $14.51 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
| 10 | Kiunga Airport UNG · Western Province | 57,736 | ×1.86 3.3%/yr | 401 m² +182 | 3 from 2 | $13.74m | $24.43 | |||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
What flies there now
Before any forecast: 10,417 scheduled departures across the ten in 2025. How much of that is Code C — the commercial turboprops and small jets that size a stand — varies enormously, from 17% at UNG to 96% at MAS.
Share of movements that are Code C
The remainder is general aviation, light aircraft and helicopters — which need parking, but not a gate. Kiunga Airport is the outlier: almost all of its recorded traffic is light aircraft.
Largest operators, all ten
Busiest routes, all ten
Port Moresby is the busiest route at every one of the ten. These are spokes, not a network.
Flights bunch into the morning
Recorded movements by hour of day. Nothing moves at night at any of the ten — which is why the peak-hour factor, not the annual total, drives every facility figure.
Where the ten go by 2045
Adopted forecast (S2). Together the ten carry 794,832 passengers in 2026 and 1,452,616 in 2045. Left of the dashed line is the record; right of it is forecast. Each airport keeps its colour throughout this page.
Growth is not uniform
Kavieng Airport more than doubles (×2.14) while Alotau Gurney Airport grows ×1.63. Two airports the same size today need different buildings in twenty years.
What has to be built
Across the ten: 4,587 m² of additional terminal floor and 6 more aircraft stands by 2045. The table below steps through the check years the report uses.
| Airport | 2026 | 2030 | 2035 | 2040 | 2045 | |||||
|---|---|---|---|---|---|---|---|---|---|---|
| Terminal m² | Stands | Terminal m² | Stands | Terminal m² | Stands | Terminal m² | Stands | Terminal m² | Stands | |
| GKA Goroka | 980 | 3 | 1,091 | 3 | 1,277 | 4 | 1,531 | 4 | 1,808 | 5 |
| WWK Wewak Boram | 1,025 | 3 | 1,029 | 3 | 1,189 | 3 | 1,412 | 3 | 1,707 | 4 |
| HKN Kimbe Hoskins | 757 | 3 | 885 | 3 | 1,032 | 3 | 1,189 | 3 | 1,465 | 3 |
| MAG Madang | 668 | 2 | 694 | 2 | 823 | 3 | 1,010 | 3 | 1,211 | 3 |
| KVG Kavieng | 535 | 2 | 694 | 2 | 823 | 3 | 960 | 3 | 1,158 | 3 |
| GUR Alotau Gurney | 446 | 2 | 422 | 2 | 532 | 2 | 604 | 2 | 729 | 2 |
| VAI Vanimo | 364 | 2 | 382 | 2 | 443 | 2 | 509 | 2 | 624 | 2 |
| MAS Manus Momote | 324 | 2 | 340 | 2 | 406 | 2 | 477 | 2 | 603 | 2 |
| BUA Buka | 292 | 2 | 305 | 2 | 363 | 2 | 424 | 2 | 490 | 2 |
| UNG Kiunga | 219 | 2 | 229 | 2 | 282 | 3 | 339 | 3 | 401 | 3 |
What it costs, element by element
Direct works split into seven elements, then utilities, design and contingency on top. Total for the ten is $129.6m in 2026 prices.
Cost does not follow demand
Kiunga Airport carries the smallest forecast of the ten — 57,736 passengers in 2045 — yet ranks 5th of ten on capital cost at $13.74m. Lighting, fire cover, fencing and service roads are largely fixed: a small airport still needs them.
When the money is spent
Three phases. Real is 2026 prices; as spent adds escalation to the midpoint of each phase. The gap across the ten is $40.0m — that is escalation, not extra work.
What each passenger would have to carry
Capital charge over 30 years at 6%, plus 3% a year for operating and maintenance, divided by 2045 traffic. Kiunga Airport needs $24.43 a passenger; Wewak Boram Airport needs $6.37.
What these numbers rest on
Shared by all ten airports
Load factor 0.45 · peak-hour factor 0.142 · directional split 0.55 · 18 m² per peak passenger. These are programme parameters, not findings about any one airport.
PNG AMPC peak-hour method — programme parameters carried in the project extract. Seats per movement is cross-checked against the OAG 2025 observed schedule
Specific to each airport
Seats per movement, the demand forecast, the observed fleet mix and the committed works. Everything else follows from these.
Adopted planning value, cross-checked against the OAG 2025 observed seats per departure at this aerodrome
Planning allowance. Consistent with the ADRM 12th Edition Exhibit 3.3.4.7 optimum space guidelines for the facilities a domestic passenger uses, with circulation, concession and back-of-house added
Where a survey would change the answer
Planning allowance for a single-apron provincial aerodrome, to be replaced by measured quantities at layout design
Median of the three PNG AMPC regional hub workbooks (Mount Hagen, Nadzab, Rabaul Tokua)
The movement record covers part of the year only — August and September are absent for all ten airports. Hour-of-day shape is usable; month-to-month totals from this record are not, and no seasonality is claimed here.